This guide walks you through estimating the total cost of running a data center, covering power, cooling, staffing, bandwidth, and maintenance. You’ll need your facility’s power draw, electricity rate, and headcount to get a realistic number.
What You’ll Need
- Total IT load in kilowatts (kW) – from server nameplates or a power meter
- Facility power usage effectiveness (PUE) – typically 1.3 to 2.0
- Local electricity rate in $/kWh
- Number of racks and average power per rack
- Monthly bandwidth usage in TB and cost per TB
- Staff count and average loaded salary
- Maintenance contracts (HVAC, generators, UPS) – annual cost
- Hardware replacement cycle (years) and total hardware value
- Facility costs: rent, insurance, security, taxes
Step-by-Step
- Calculate total IT power draw. Add up the nameplate power of all servers, storage, and networking gear. If you have a power meter, use the actual measured load, which is usually 30–50% lower than nameplate.
- Estimate facility power draw. Multiply the IT load by your PUE. For example, 500 kW IT load with a PUE of 1.5 means the facility draws 750 kW total.
- Compute annual electricity consumption. Multiply facility kW by 8,760 hours per year. For 750 kW, that’s 6,570,000 kWh per year.
- Calculate electricity cost. Multiply annual kWh by your blended electricity rate (including demand charges). At $0.10/kWh, that’s $657,000 per year.
- Add cooling costs. If your PUE already includes cooling, skip this. Otherwise, cooling typically adds 30–50% to the electricity bill. Use the difference between your PUE and 1.0 to estimate the cooling portion.
- Estimate bandwidth costs. Multiply your monthly usage in TB by the cost per TB, then multiply by 12. Many providers charge $5–$20 per TB, but this varies widely.
- Calculate staffing costs. Multiply the number of staff by their average fully loaded salary (base + benefits + taxes). Include 24/7 operations staff, engineers, and management.
- Add maintenance and support contracts. Sum annual costs for HVAC, generators, UPS, fire suppression, and server hardware support.
- Include hardware replacement costs. Divide the total value of your IT hardware by its expected lifespan (usually 3–5 years). This gives an annual depreciation cost.
- Add facility costs. Include rent or mortgage, property taxes, insurance, and physical security (guards, cameras).
- Sum all costs. Add electricity, bandwidth, staffing, maintenance, hardware depreciation, and facility costs to get your annual total.
- Convert to monthly or per-rack. Divide by 12 for monthly, or by the number of racks for cost per rack.
Common Mistakes
- Using nameplate power instead of actual. Nameplate ratings are maximums; actual draw is often much lower. Using nameplate overestimates costs by 30–50%.
- Ignoring PUE. If you forget to multiply by PUE, you’ll undercount the power bill significantly.
- Forgetting demand charges. Many utilities charge extra for peak power usage. Include these in your $/kWh rate.
- Omitting staffing. Labor is a major cost, often 30–40% of total. Don’t skip it.
- Not accounting for redundancy. N+1 or 2N designs use more power and maintenance. Adjust PUE and maintenance accordingly.
- Using a single flat rate. Electricity rates vary by time of day and season. Use a blended average or a time-of-use model.
Tips
- Measure, don’t guess. Use a power meter or DCIM tool to get real IT load data.
- Track PUE over time. PUE changes with outside temperature and load. Use an annual average.
- Include all facility costs. Don’t forget water for cooling, fire suppression refills, and environmental monitoring.
- Use a spreadsheet. Build a model that lets you adjust inputs and see the impact.
- Compare with industry benchmarks. The Uptime Institute publishes average PUE and cost per kW. Use these to sanity-check your numbers.
- Plan for growth. Add a buffer for future expansion, typically 10–20%.
Troubleshooting
- Your estimate seems too high. Check if you used nameplate power. Re-measure actual draw. Also verify your PUE – a PUE of 2.0 may be realistic for an older facility, but 1.3 is common for modern ones.
- Your estimate seems too low. You may have missed demand charges, staffing overhead, or maintenance contracts. Review each category.
- Electricity rates vary wildly. Contact your utility for a breakdown of energy, demand, and fixed charges. Use the effective rate.
- You don’t know your PUE. If you don’t have a measurement, use 1.5 as a conservative default for a typical air-cooled facility.
- Costs differ month to month. Seasonal cooling loads cause variation. Use an annual average.
- Hardware lifespan is uncertain. Use 4 years as a default, but adjust based on your refresh cycle.
Frequently Asked Questions
What is the biggest cost in a data center?
Electricity is usually the largest single cost, followed by staffing. Power can be 30–50% of operating expenses.
What is a typical PUE?
Modern efficient facilities achieve 1.2–1.4. Older or poorly optimized ones may be 1.8–2.0. The industry average is around 1.5.
How do I estimate cooling costs separately?
Cooling is roughly (PUE – 1.0) times the IT load. For example, with PUE 1.5, cooling uses 0.5 kW for every 1 kW of IT load.
Should I include depreciation?
Yes, for a total cost of ownership. Hardware replacement is a real future expense. Use straight-line depreciation over 3–5 years.
How can I reduce data center costs?
Improve PUE by optimizing airflow, raising temperature setpoints, and using free cooling. Consolidate servers to reduce IT load. Negotiate electricity rates and bandwidth contracts.
What is the cost per rack?
Divide the total annual cost by the number of racks. Typical values range from $10,000 to $50,000 per rack per year, depending on density and efficiency.
Related
Method: the standard formula for this calculation, rounded as each result states. See how the calculators work or report an error.
More cards in this drawer
- Philips DST7060/20 7000 Series Iron: Specs & Fit
- Coal Fueled Jet Aircraft: Could It Work?675 L
- Remote Desktop on Raspberry Pi: How to Enable It
- Word Select Last Line in Paragraph?
- Google Assistant IFTTT Recipes: 7 Useful Automations
- OLED TVs in Dark Rooms: Why They Look Better and When They Don’t